skip to content

Woodlawn Zinc-Copper Project

Operations

With the completion of financing in September 2017, 2018 was a year of construction and activity at the Woodlawn Project site. Commissioning activities commenced in late 2018 and will continue to progress through stages to full production rates in first quarter 2019 when first production is expected.

The Company expects to deliver the first shipment of concentrate to market in early 2019.

Underground

Underground Ore Configuration

Heron awarded its contract for Underground Mining operations to Pybar Mining Services in early 2018 with preparatory work for mobilisation to site progressing to achieve a target of a third quarter 2018 start date.

At the end of the September quarter, access works to the underground had included final ground support to the box cut and the initial few metres of decline development advance that signified the commencement of the Woodlawn Underground Mine. The completion of the G2 drilling in the year has provided the opportunity to access earlier production for the first ore with mine planning work being revised to include this into the activity schedule.

Tailings Retreatment

Reclaimed Tailings Ore configuration

The hydraulic mining operation at Heron’s Woodlawn site, alongside the underground operations that commenced in September 2018, will provide a second ore source to be processed through the new processing plant. The hydraulic mining operation covers the hydraulic monitors and the associated high-pressure water, reclaim and slurry transfer pumps.

The mining equipment supply, installation and commissioning contract for Heron’s Tailings Mine operations and specialist hydraulic mining services contract were awarded in May 2018 to National Pump & Energy and Paragon Tailings Australia respectively.

This combination of project partners brought together a complementary skill set of proven equipment supply and operational expertise to the tailings hydraulic mining operations at Heron’s Woodlawn Mine.

Hydraulic tailings retreatment preparations commenced in late December 2018, with infrastructure energised and water testing underway in December 2018. The commissioning activities involved the functional testing of equipment in the circuit including the commissioning of the trash screen and transfer pumps at the transfer station.

Processing

Processing
Processing

Two sources of ore from underground and tailings operations will be processed through the processing plant at Heron’s Woodlawn site to produce three concentrates – zinc, copper and lead.

One of the best examples of the advances made in sulphide processing technology and forming an integral component of the Woodlawn processing plant is the 3MW IsaMillTM.

The IsaMillTM is manufactured in Germany and first entered commercial use in 2000. It now represents proven technology, taking on grinding applications in a large number of global mining operations.

Having become available after Woodlawn’s former operations ceased in 1998, this piece of equipment provides the critical fine grinding capability to reduce the flotation feed to 30microns in size. Test work has demonstrated this sizing to be the most effective to liberate the different zinc, copper and lead sulphides, allowing for the highest recoveries to Heron’s base metal concentrates.

Shipping/Logistics

The Woodlawn site will produce three separate mineral concentrates – Zinc, Copper and Lead which will be exported via Port Kembla and Port Botany. The concentrate is moved between the mine site and the ports using a dedicated fleet of sealed containers.

The domestic logistics chain for Woodlawn concentrate export will comprise a small fleet of semi-trailers moving containers between Goulburn and the mine site, the use of a container storage facility in Goulburn, and the transfer of containers on to rail services running between Goulburn, Port Botany and Port Kembla.

At the conclusion of a tender process, Heron awarded its significant transportation services contract to Goulburn-based road and rail services provider, Crawfords Freightlines Pty Limited in June 2018.

Heron had initially planned to move the containers entirely by road haulage to the ports but in evaluating the opportunities for transportation, identified an attractive and cost-effective opportunity to utilise a rail yard in Goulburn (approximately 50km north of the mine site) to undertake a transfer from road to rail. Use of this intermodal has the advantages of reducing the annual road movements and eliminating truck movements through Goulburn.

Rail container transport services
Road container transport services